  1. Words used in this lesson
  2. Where the three letters come from
  3. Choosing an SLI: start from the user
  4. From SLI to SLO: how good is good enough?
  5. The nines, converted into minutes
  6. Error budgets: the allowed amount of failure
  7. Measuring things, and deciding which ones to promise
  8. Errors and toil: the other use of the budget
  9. Common mistakes
  10. Try it
  11. Interview questions
  12. Key takeaways
  13. What's next

In one line: "reliable" is not a feeling. An SLI is a number that measures what users feel (for example, the share of requests that succeeded fast enough), an SLO is the target you promise yourself for that number, and the error budget is the small amount of failure the target allows, which you are meant to spend on shipping things, and to stop spending when it runs out.

Ask a team "is the service reliable?" and you get answers like "mostly", "yes, except on Mondays" or "the CEO says no". None of those can be graphed, argued over or used to decide anything. Ask "did 99.9% of checkout requests succeed this month?" and you get a number, a yes or a no, and a clear next step.

This is lesson 4 of nine. The three lessons before it gave us the raw data: logs, metrics and traces. This lesson turns the data into targets. The next lesson, Alerting and Dashboards That People Trust, uses the targets to decide who gets woken up. Lesson 5 goes deep on burn-rate alert rules, so here I only explain what a burn rate is and why it is a good number. The lesson after that, Incidents, On-Call and Blameless Post-Mortems, uses the budget to rate how bad an incident was.

You need no maths beyond percentages. Every number in this lesson came out of a small script I ran, and I show the scripts.

What I ran / checked. Linux, Node.js v22.22.0 for all the scripts (nines.mjs, sli.mjs, budget.mjs, policy.mjs, burn.mjs). For the Prometheus recording rules I used the promtool binary I built from the prometheus/prometheus module (tag v0.315.0, the same build as in lesson 5; its version string is empty because of how I built it). The traffic in the scripts is fake, made by a random generator with a fixed seed so the output is the same every time. The incidents are invented. Sources I read (in my own words): the README of the open-source slok/sloth project (an SLO generator for Prometheus), which describes SLI recording rules over several time windows and the multi-window, multi-burn-rate alert approach. Could not reach: sre.google (the Google SRE book and workbook chapters on SLOs) was blocked by my sandbox, and the OpenSLO specification files I tried returned 404 or an empty page. So the vocabulary and the "about 50% of budget used, then review" style of policy below come from my own knowledge of how teams commonly work, not from a page I read this week. The maths is mine and is shown. Check the Google chapters yourself before quoting them. I did not check any GitHub star counts.

Words used in this lesson

  • An SLI (service level indicator) is a measurement of how well the service is doing, from the user's point of view. It is usually a ratio: good events divided by valid events.
  • An SLO (service level objective) is a target for an SLI over a time window, such as "99.9% of requests succeed over 30 days".
  • An SLA (service level agreement) is a promise to a customer, usually in a contract, with a penalty such as a refund if you miss it. It is looser than your internal SLO.
  • Good event, valid event, bad event. A valid event is one that counts at all. A good event is a valid one that went well. A bad event is a valid one that did not.
  • Availability is the share of requests (or time) in which the service works.
  • The nines is the habit of writing targets as 99.9% ("three nines"), 99.99% ("four nines") and so on.
  • Error budget is how much failure the SLO allows: 100% minus the SLO. For 99.9% it is 0.1%.
  • Burn rate is how fast you spend the error budget, compared with the speed that would use it up exactly at the end of the window. Burn rate 1 means "on plan". Burn rate 10 means "ten times too fast".
  • SLO window is the period the SLO covers. It can be a rolling window (the last 30 days, always moving) or a calendar window (this month).
  • Error budget policy is a short written agreement about what the team does when the budget gets low or runs out.
  • Toil (a word from SRE) is repetitive manual work that grows with the service and has no lasting value. We only touch it at the end.

Where the three letters come from

Three terms, three audiences:

TermWhat it isWho it is forExample
SLIA measurementEngineersShare of checkout requests that returned without a 5xx error and in under 300 ms
SLOA target for that measurement, over a time windowThe team and its product ownerThe SLI is at least 99.9% over 30 days
SLAA promise with consequencesCustomers and lawyersIf monthly uptime is under 99.5%, the customer gets 10% credit

Notice the order: you first measure (SLI), then you decide how good is good enough (SLO). The SLA, if you have one, is set looser than the SLO. If your SLO is 99.9% and your contract says 99.5%, you will notice and fix trouble before you owe anybody money. An SLA that is as tight as the SLO means you find out about problems at the same moment you start paying for them.

Not every service has an SLA. Almost every service benefits from an SLO, even a private one. An SLO is a tool for your own team to decide how much risk is fine.

Choosing an SLI: start from the user

The best SLI is a number that goes down when users are unhappy and stays flat when they are not. It sounds obvious. In practice teams often choose what is easy to collect: CPU use, memory, disk, number of pods. These are useful for debugging, but users do not feel CPU. They feel a page that does not load.

A simple recipe is to think in user journeys and pick the right shape of SLI for each:

What the service doesSLI typeGood eventValid event
Answers requests (APIs, web pages)AvailabilityResponse was not a server errorA real request we should have served
Answers requestsLatencyResponse came in under a threshold (say 300 ms)A request that was served at all
Moves or stores dataFreshnessData is newer than, say, 5 minutesA reading of the data
Processes data in batchesCorrectnessOutput matched what a checker expectsA processed record
Stores dataDurabilityA read returns what was writtenA read of data we promised to keep
Background jobsThroughput or completionThe job finished before its deadlineA scheduled job

You do not need all of them. For most web services, two cover most of what users feel: availability and latency. Start there.

Write the SLI as "good divided by valid"

Almost every good SLI has this shape:

TEXT
SLI = good events / valid events

This has three nice properties. It is always between 0 and 1 (or 0% and 100%), so every SLI looks the same. It scales: ten requests or ten million requests, the same formula. And it makes you think about two questions that matter a lot: what counts as valid? and what counts as good? Most arguments about SLOs are really arguments about those two words.

Let me show how much they matter. I generated 200,000 fake requests for one day of a checkout service. About 2% are health checks from the load balancer, 3% are bots, and the rest are real user traffic. Some user requests fail with a 500 (our fault), some return 404 (the user asked for something that does not exist), a few return 429 (we rate-limited them), and about 1% are slow. The script is sli.mjs:

TEXT
total requests: 200000naive  availability (all traffic, 5xx bad): 99.9145%valid events: 189632  bad: 233careful availability SLI: 99.8771%

Same day, same traffic, two numbers: 99.9145% and 99.8771%. The naive version counted everything and called only 5xx bad. It was too kind in two ways. The denominator included health checks and bots, which almost never fail. And it ignored the 429 responses, which are failures from the user's point of view even though they are a "client error code", because we chose to turn those users away.

My careful version made these rules, written down so everybody can argue about them:

  • Valid means: a real user request. Health checks and bot traffic are excluded. Also excluded: 404 and 403 answers, since the user or the bot asked for something that was never ours to give.
  • Bad means: a 5xx response, or a 429 (we refused a real user).

You may disagree with those exact rules. Good. The point is that the rules are visible. If you write "availability" on a dashboard and nobody knows what is in the denominator, the number will be used for a decision and the decision will be wrong.

Do not measure where it is easy, measure where it hurts. If your SLI comes from the application's own metrics, a crash, a full queue or a dead load balancer shows up as no data, not as errors. A request that never reached your code is a failed request for the user. Where you can, measure at a point close to the user, such as the load balancer or the edge, and consider an external probe too. Application metrics are great for debugging, but they cannot see failures that happen before your code runs.

Latency SLIs: use thresholds, not averages

Lesson 2 showed why averages lie. The same rule applies here. A latency SLI is not "average latency is below 200 ms". It is again a good-divided-by-valid ratio: the share of requests that finished under a threshold.

From the same fake day:

TEXT
latency SLI  < 100  ms: 62.083%latency SLI  < 200  ms: 91.855%latency SLI  < 300  ms: 97.486%latency SLI  < 500  ms: 98.777%latency SLI  < 1000 ms: 99.539%p50 82 p90 185 p99 639 p99.9 1236 mean 109.8

The mean is 109.8 ms and sounds great. But 2.5% of requests were slower than 300 ms, and p99 is 639 ms. Now compare what the two ways of speaking promise:

  • "p99 latency under 300 ms" is a statement about one number from a percentile. It is hard to add up over time, because you cannot average percentiles from different minutes into a correct monthly percentile (lesson 2).
  • "97.5% of requests are faster than 300 ms" is a ratio of counts. You can add counts over any period and any number of servers. That is why SLO tooling prefers it, and why a histogram with a bucket boundary exactly at your threshold (0.3 s) is the right metric to have.

Both say almost the same thing, but only the second one adds up correctly.

A subtle point: the thresholds and targets come as a pair. "97% under 300 ms" and "99.9% under 1 second" can both be SLOs for the same endpoint. This is a normal and good pattern: most requests should be quick, nearly all should be not-terrible.

Combining success and speed

A user does not care why a request was bad. A fast error and a slow success both hurt. Some teams therefore define one SLI: a request is good if it succeeded and was fast enough. On the same day:

TEXT
combined good-event SLI (ok and <300ms): 97.3665%

That is the number of requests that did what the user wanted, in time. It is lower than either part alone, as it must be. One combined SLI is simple to alert on and to explain. Two separate SLIs are easier to debug. Pick whichever your team will actually read, and do not spend a month deciding.

How to produce the SLI in Prometheus

If your service exports the usual http_requests_total{code=...} counter and an http_request_duration_seconds histogram (lesson 2), you can store the SLI as recording rules. Here is mine. The two ratios use the same "good over valid" shape:

YAML
groups:  - name: checkout-sli    rules:      - record: job:checkout_requests:rate5m        expr: sum(rate(http_requests_total{job="checkout"}[5m]))      - record: job:checkout_bad_requests:rate5m        expr: sum(rate(http_requests_total{job="checkout", code=~"5.."}[5m]))      - record: job:checkout_availability:ratio_rate5m        expr: |          1 - (            job:checkout_bad_requests:rate5m            /            job:checkout_requests:rate5m          )      - record: job:checkout_latency_good:ratio_rate5m        expr: |          sum(rate(http_request_duration_seconds_bucket{job="checkout", le="0.3"}[5m]))          /          sum(rate(http_request_duration_seconds_count{job="checkout"}[5m]))

I checked the syntax and then tested it with promtool test rules, feeding in made-up series: 990 good and 10 bad requests every minute, and a histogram where 950 of every 1000 requests fall in the le="0.3" bucket.

TEXT
Checking sli-rules.yml  SUCCESS: 4 rules found  SUCCESS

The test expected an availability of 0.99 and a latency-good ratio of 0.95, and passed. To be sure the test could fail, I changed the expected latency to 0.90, and it printed FAILED with exp: 9E-01 got: 9.5E-01. One real-world detail: in a promtool test, the expected labels of a recorded series have to include the metric name (I wrote labels: 'job:checkout_availability:ratio_rate5m'), otherwise a test that looks right reports a failure. My first try with labels: '{}' failed that way.

Notice that I left out the health-check and 404 filtering, to keep the rules short. In real life you would add label filters (route!="/healthz", code!~"404|403") to match the "valid" definition you wrote down. The slok/sloth project, which I read about, generates this kind of recording rules and the alert rules from a short SLO spec, for several time windows at once. That is useful when you have many services. For one or two, hand-written rules are fine.

Counting le="0.3" only works if that bucket exists. The histogram can answer "how many were under 0.3 s" only when 0.3 is one of its bucket boundaries. If your buckets are 0.25 and 0.5, you cannot compute a 300 ms SLI exactly. Choose your bucket edges around your SLO thresholds before you need them.

From SLI to SLO: how good is good enough?

An SLO is a target on the SLI over a window. The shape is always the same: an SLI, a target, and a time window. For example:

TEXT
99.9% of valid checkout requests succeed, measured over a rolling 30 days.97%   of valid checkout requests finish in under 300 ms, over a rolling 30 days.

How do you pick the number? The honest answer: by asking what users need and what you can pay for, and then adjusting with data.

  • Look at what you actually achieved over the last few months. If you ran at 99.95%, a 99.9% SLO is realistic. A 99.99% SLO would be a leap that needs money and design change.
  • Remember the SLO is not a wish. It is a trade-off. Each extra nine costs more, and (see below) it also slows you down, because you can afford less change.
  • Your service cannot be more reliable than the things it depends on, unless you design for it (see the dependency section).
  • Users are often fine with less than you think. An internal report page does not need the same SLO as a payment API. A phone connection, the user's own Wi-Fi and the browser fail often anyway, so past some point extra reliability on your side is invisible to the user.
  • Start with a lower target you can meet and tighten later. It is much easier to raise a target than to explain a missed one.

Never set an SLO of 100%. It is impossible (the network, the cloud provider and the user's laptop all fail sometimes), and it means any change at all is "too risky" because the budget is zero. A target that can never be met also teaches the team to ignore it.

Rolling or calendar window?

  • A rolling window (the last 30 days, recomputed all the time) matches how users remember: "it has been bad lately". It never "resets", so a bad day keeps counting until it falls out of the window 30 days later. This is smooth and hard to game.
  • A calendar window (this month) is easy to put in a report, and the budget refreshes on the first day. The weakness: a team that blew the budget on the 3rd has no reason to be careful until the 1st of next month, and a team that is fine on the 29th can ship something risky because "it resets tomorrow".

Neither is wrong. Many teams use a rolling 28 or 30 days for alerting and decision-making, and a calendar month for reporting to others. The important thing is to pick one and write it down.

The nines, converted into minutes

Percentages are hard to feel. 99.9% and 99.99% look almost the same on a slide, but they are very different in practice. So let us translate. The allowed bad share is 1 - SLO, and if we count by time, it times the length of the window. Here is nines.mjs:

TEXT
SLO       per 30 days   per 90 days   per year90        3.00 d        9.00 d        36.50 d99        7.20 h        21.60 h       3.65 d99.5      3.60 h        10.80 h       1.83 d99.9      43.20 min     2.16 h        8.76 h99.95     21.60 min     1.08 h        4.38 h99.99     4.32 min      12.96 min     52.56 min99.999    25.9 s        1.30 min      5.26 min

Learn two rows by heart. 99.9% is about 43 minutes a month. 99.99% is about 4 minutes a month. Each extra nine divides the allowed downtime by ten.

Now think about what four minutes means. A human gets paged, wakes up, finds a laptop, opens a dashboard and starts to look. That alone takes more than four minutes. So with a 99.99% target and a human in the loop, one incident can use the entire month. To meet four nines you need automatic failover and automatic rollback, not heroic on-call. At five nines (26 seconds a month) humans are out of the picture altogether.

That is why the cost of each nine is not small. Consider what you must buy as you go up:

TargetWhat it usually needs
99%A single server and a decent deploy process is almost fine
99.9%Redundancy (more than one instance), health checks, quick rollbacks, a real on-call
99.99%Several zones, automatic failover, automatic rollback, tested runbooks, careful releases
99.999%Several regions, no single point of failure anywhere, and a very large engineering team

Not every request or user is equal, either. "Time-based" availability counts minutes of downtime. "Request-based" availability counts requests. They behave differently. My policy.mjs script has the same 10-minute total outage at two times of day:

TEXT
10-minute total outage:at peak                traffic 3500 req/min  budget used (request-based): 40.51%   (time-based: 10/43.2 min = 23.15%)at the quietest time   traffic 500 req/min  budget used (request-based): 5.79%   (time-based: 10/43.2 min = 23.15%)

A time-based view says both outages cost the same: 10 of the 43.2 allowed minutes (23%). A request-based view says the peak outage hurt seven times more, since seven times more users were affected. Request-based is usually fairer, because it counts what users felt. It also means the budget "in minutes" is only an estimate. The budget in requests is the real thing. (In my fake traffic the daily average is about 2,000 requests a minute, so a peak minute costs more than an "average" minute. That is why the 40.5% is more than 23%.)

Your dependencies set a ceiling

A request that needs three services in a row works only if all three work. For independent parts, you multiply their availabilities:

TEXT
Serial chain: a request needs ALL parts to work3 x 99.9%          99.7003% downtime/30d: 2.16 h5 x 99.9%          99.5010% downtime/30d: 3.59 h10 x 99.9%         99.0045% downtime/30d: 7.17 h99.99 + 3 x 99.9   99.6903% downtime/30d: 2.23 hParallel (two independent replicas, either is enough)2 x 99% -> 99.9900%2 x 99.9% -> 99.9999%

Three dependencies at 99.9% each give you 99.7%. Ten give you 99.0%. And the last serial line shows the main trick for SLO setting: one 99.99% part does not rescue three 99.9% parts. The weakest links dominate. In the other direction, putting two independent copies in parallel turns two 99% parts into 99.99%. That is the whole reason for redundancy.

Two cautions on those numbers. First, they assume the parts fail independently. Two replicas that run the same code on the same database fail together, so the parallel result is too optimistic. Second, real systems also degrade gracefully (lesson 7): if the recommendations service is down, you can still show the page without recommendations, so that dependency is not really "in series". A good way to raise your effective availability is to make dependencies soft instead of hard.

Error budgets: the allowed amount of failure

Now the central idea. If the SLO is 99.9%, then 0.1% of requests may fail and you are still within target. That 0.1% is the error budget.

TEXT
error budget = 1 - SLO

The word "budget" is the point. A budget is something you are supposed to spend. A team that finishes the month with 100% of its budget unspent was too careful: it could have shipped more, tried more, taken more risks. A team that spent 300% was too reckless. The target is to spend it wisely.

Here is a month in my invented checkout service: 30 days, request counts that rise and fall through the day (between 500 and 3,500 requests a minute), a background error rate of 0.02%, and four incidents. The script is budget.mjs:

TEXT
requests in window: 86,400,000budget (allowed bad requests): 86,400bad requests actually: 53,185SLI for the month: 99.9384%budget spent by each cause (share of the full-month budget)bad deploy            3.0%slow leak             1.9%dependency down      35.9%cache stampede        0.8%background errors    20.0%

The SLO was 99.9%, the result was 99.9384%, so we met it and have 38% of the budget left. Read the list of costs. Five different causes, and one of them, a 10-minute total outage of a dependency, ate 36% of the whole month's budget by itself. The "bad deploy" (2% errors for 40 minutes) cost only 3%. A short, total failure is far more expensive than a long, small one. And look at the last line: 20% of the budget went on background errors, the steady drip of 0.02% nobody ever paged for. Incidents are not the only budget-spenders. A small constant leak is a real cost, and the budget makes it visible.

Here is the same month day by day. "Budget used of month" is the share of the full month's budget that had been spent by then:

TEXT
day  SLI-so-far   budget-used-of-month  1    99.9800%          0.7%  3    99.9800%          2.0%  4    99.9578%          5.6%  5    99.9622%          6.3% 10    99.9711%          9.6% 11    99.9719%         10.3% 12    99.9678%         12.9% 19    99.9723%         17.5% 20    99.9727%         18.2% 21    99.9217%         54.8% 26    99.9329%         58.1% 27    99.9338%         59.6% 30    99.9384%         61.6%

Between day 20 and day 21 the budget jumped from 18% to 55% in one day: that is the dependency outage. This is the shape of most reliability stories: long flat stretches, then a step. A line like this on a dashboard tells everybody, in one second, how much room the team has.

The SLI so far can look worse than the budget. On day 4 the SLI-so-far is 99.9578%, which is "within 99.9%", yet 5.6% of the whole month's budget is already gone. Both statements are true. Be clear which one your dashboard shows. "Percent of budget remaining" is the easiest to understand, so show that one.

Burn rate: how fast are we spending?

The budget is a stock, like money in a bank. The burn rate is the speed of spending. If errors run at exactly the allowed rate (0.1% for a 99.9% SLO), the budget lasts the whole window. That is a burn rate of 1. If errors run at 1%, we burn ten times faster. Burn rate is simply:

TEXT
burn rate = current error ratio / error budget

burn.mjs shows the table for a 99.9% SLO over 30 days:

TEXT
error ratio   burn rate   whole budget gone in  0.05%         0.5x    60.0 days  0.10%         1.0x    30.0 days  0.20%         2.0x    15.0 days  1.00%        10.0x    3.0 days  5.00%        50.0x    14.4 hours 50.00%       500.0x    1.4 hours100.00%      1000.0x    43.2 minutes

The last row is the number from the nines table: at a total outage, the monthly budget (43.2 minutes) is gone in 43.2 minutes. A 1% error rate sounds small, a clean "99% success", but at a 99.9% SLO it burns ten times too fast and the month's budget is gone in three days.

The burn rate has a big advantage over the raw error rate: it does not depend on the SLO. "5% errors" is serious for a 99.9% service and a disaster for a 99.99% service. "Burn rate 50" means the same level of urgency in both cases. That is why lesson 5 builds alerts on burn rate: one rule, any service. I will not repeat the alert rules here.

What the budget is for

This is the part most beginners miss. Error budgets are not mainly a way to blame anybody. They are a decision tool for the argument that every company has:

  • Product says: "ship faster, we are losing to competitors."
  • Operations says: "slow down, every release is a risk."

Without a number, the loudest voice wins. With an error budget, both sides agree on the rules in advance:

  • If there is budget left, ship. Go ahead with the risky migration, the experiment, the dependency upgrade. Failure is expected inside the budget. That is what it is for.
  • If the budget is nearly spent or gone, slow down. Put effort into reliability: fix the top cause of failures, add the missing test, improve rollback. New features wait.

An agreement like this is called an error budget policy. Mine is short on purpose. A real policy is a page, agreed with the product owner before anything goes wrong, so that nobody has to invent it at 2 a.m.:

TEXT
Budget policy for checkout (30-day rolling window, SLO 99.9%)- Under 50% used:      normal work.- 50% to 80% used:     risky changes need a second reviewer and a rollback plan.- 80% to 100% used:    only low-risk changes. Fix the top cause of bad requests.- 100% used or more:   feature freeze. Only reliability work and security fixes ship                       until the SLI is back above target.- A single incident that uses over 20% of the budget gets a written post-mortem.

I tested the idea on a rougher version of the same month, with an extra 90-minute incident on day 23 where 35% of requests failed. policy.mjs applies the policy as time goes by:

TEXT
day 21 09:13  50% used: review risky changesday 24 13:16  80% used: only low-risk changesday 24 13:31  100% used: feature freeze, reliability work onlyend of month: used 183.2% of budget, SLI 99.8168%

Look at the dates. The outage on day 21 crossed 50%. The extra incident then took the team from 80% to 100% in fifteen minutes. A budget policy does not prevent that, because nothing can. What it provides is the rule for what happens next: the freeze starts at 13:31 on day 24 and nobody needs a meeting to decide. The SLO was missed (99.82% against 99.9%), and the missed SLO is not a disaster by itself. It is a signal that says "stop adding risk and fix reliability now".

Note how this solves the political problem. The freeze is not "operations being difficult". It is something that the product owner agreed to when the policy was written. And in the other direction: when the budget is healthy, operations cannot say "no" to a reasonable launch just because change is scary.

A budget policy only works if somebody has the authority to enforce it. If the freeze can be waved away by a manager every time, the SLO is decoration. Get the product owner (and the manager above them) to sign the policy while things are calm.

Budgets also say something about over-achievement. If a service has run at 99.99% for a year against a 99.9% SLO, it has been spending a tenth of its budget. Either the SLO is too low, or the team has been too careful and could have shipped faster. A few teams even do planned small outages to keep dependants honest, so that nobody quietly relies on a level of reliability that was never promised. You do not need to do that, but the thought is useful: reliability above what users need is waste.

Low traffic makes budgets jumpy

The budget is a count of bad requests, and when counts are small, each single failure is large. burn.mjs shows:

TEXT
Low-traffic service, SLO 99.9%, 30 days    500 req/day -> 15,000 per month, budget = 15.0 bad requests, one failure = 6.7% of the budget   5000 req/day -> 150,000 per month, budget = 150.0 bad requests, one failure = 0.7% of the budget 500000 req/day -> 15,000,000 per month, budget = 15000.0 bad requests, one failure = 0.0% of the budget

With 500 requests a day, a 99.9% SLO allows 15 failures a month. Two bad minutes can eat it. The SLI becomes noisy and alerts become either useless or constant. For small services, the fixes are: use a longer window (a quarter), use a looser SLO, add synthetic probes (a script that sends a test request every minute, so there is always a steady flow of events), or count at a higher level (one SLO for the whole product, not one per tiny endpoint). The opposite problem also exists: a huge service where 0.1% is still 15,000 failed requests, which may be many unhappy real people. Percentages hide absolute numbers, so keep the counts visible too.

Measuring things, and deciding which ones to promise

A few practical rules from running SLOs:

  1. Keep the count small. Two to four SLOs per service (usually availability and latency of the most important journeys) are better than 30. A long list nobody reads is the same as no list.
  2. Pick critical journeys. "Login", "search", "checkout", "upload". An SLO on "the whole API" can look healthy while checkout is on fire, because the large amount of cheap, easy traffic hides the failures. If one endpoint matters much more than the rest, give it its own SLO.
  3. Write down the definition in one place. What is valid, what is good, where it is measured, which window, who owns it. The OpenSLO project exists to put this in a standard YAML format; I could not read its specification this week, so I only mention it as something to look up.
  4. Review the SLO now and then. After each quarter ask: did the SLO match user complaints? If users were angry while the SLO was green, the SLI is measuring the wrong thing. If the SLO was red and nobody cared, it may be too strict.
  5. Do not set SLOs for things users cannot feel. "CPU under 70%" is a resource alert or a dashboard line, not an SLO.

The first sign that an SLI is wrong is the "watermelon" effect: green on the outside, red on the inside. The dashboard says 99.95% and the support inbox is full. That means you are measuring something other than what users experience, so go back to the SLI.

Errors and toil: the other use of the budget

One more way to use an error budget is to compare the cost of each cause. In the month above, a short dependency outage cost 36%, and the steady background leak cost 20%. That changes what you should fix first. A dashboard of "budget spent by cause" tells you where an engineering week buys the most reliability. This is more honest than fixing whatever was loudest last week. It also connects to lesson 6: each incident can be reported as "this used 36% of the monthly budget" which gives people who were not there a feel for the size without a long story.

SRE teams use the word toil for manual, repetitive work that grows with the service. A common rule of thumb, from the same SRE material, is to keep toil below about half of an engineer's time so that the rest goes to automation and reliability projects. I could not verify the exact number this week, so treat "about half" as a guide only. The link to this lesson: when budget policy forces reliability work, the right target is often the thing that causes toil and incidents at the same time.

Common mistakes

  • Measuring what is easy, like CPU, instead of what users feel.
  • Not saying what "valid" means. Health checks and bots in the denominator make the SLI look better than the truth. Our two numbers differed by almost four hundredths of a percent, which is more than a third of the whole 99.9% budget.
  • Using averages or a single percentile for latency, instead of the share of requests under a threshold.
  • Choosing too many nines. Each one costs ten times more and allows ten times less change.
  • SLO equals SLA. Keep the internal target stricter than the promise.
  • No policy. An SLO with no agreed consequence is a number on a wall.
  • Everything is an SLO. Pick a few critical journeys.
  • Calendar-month surprises. Teams who think the budget "resets" and do risky things in the last days.
  • Never looking at the green side. Unspent budget over many months is a signal that you can move faster.

Try it

  1. A service has an SLO of 99.95% over 30 days. How many minutes of total outage does it allow? What is the burn rate when the error ratio is 0.5%, and how long until the budget is gone?
  2. You have 1,000,000 valid requests a day. You see 1,800 of them fail in one bad hour. At a 99.9% SLO over 30 days, what share of the monthly budget did that hour use?
  3. Your product calls a payment provider (99.95%), your own database (99.99%) and a search service (99.9%) in series for every order. What is the best availability you can promise for orders, ignoring your own code?
  4. Define good and valid events for a "photo upload" journey and for a "daily report email" job.
  5. Your SLO dashboard is green at 99.97% but support tickets about slow pages doubled. List three things you would check about the SLI.

Answers

  1. The budget is 0.05% of 43,200 minutes, which is 21.6 minutes. A 0.5% error ratio is 0.5 / 0.05 = a burn rate of 10. At burn 10, a 30-day budget is gone in 3 days.
  2. The monthly budget is 0.1% of 30,000,000 requests, which is 30,000. The bad hour used 1,800, which is 6% of the monthly budget.
  3. 0.9995 x 0.9999 x 0.999 = 0.99840 about, so roughly 99.84%. That is less than 99.9%, which is the target of the weakest link, so you cannot honestly promise 99.9% unless you make one of those dependencies soft (for example, a fallback for search).
  4. Photo upload: valid = an upload attempt with a file of allowed type and size; good = it was stored, readable, and finished within a time limit such as 10 seconds. Daily report: valid = a scheduled report; good = the email was sent before 08:00 and had the right data (a freshness and correctness SLI).
  5. (a) Is the SLI only availability, with no latency target? (b) Is the latency measured as an average or a high threshold that hides slowness, and is the threshold in line with what users call slow? (c) Is it measured close to the user, or only inside the app, and does the denominator include cheap health checks or bots?

Interview questions

What is the difference between an SLI, an SLO and an SLA? (Must know)

An SLI is a measurement, such as the share of requests that succeed. An SLO is a target for that measurement over a window, like 99.9% over 30 days. An SLA is a contractual promise to customers with a penalty if missed. The SLO is internal and stricter than the SLA, so I get an early warning before I owe anybody money. Many services have SLOs and no SLA.

How would you choose SLIs for a new web service? (Must know)

I start from user journeys, not from machine numbers. For each important journey (login, search, checkout) I pick availability, meaning the share of valid requests that did not fail, and latency, meaning the share of requests under a threshold. I write each as good events over valid events and I define "valid" clearly, so health checks and bots do not inflate the number. I measure as close to the user as I can, for example at the load balancer, plus a synthetic probe. Then I look at the last few months of data before choosing a target.

What does 99.9% availability mean in minutes? And 99.99%? (Must know)

Over 30 days 99.9% allows about 43 minutes of full outage, and 99.99% about 4.3 minutes. Each additional nine divides the allowed time by ten. I add that four nines usually means automation: a human cannot even wake up and look in four minutes, so I need automatic failover and rollback.

What is an error budget and what is it for? (Must know)

It is the failure the SLO allows, 100% minus the SLO. For 99.9% that is 0.1% of requests. It is for deciding how much risk to take. While there is budget, the team ships and experiments, and some failure is expected. When the budget is nearly or fully spent, the team slows down on features and works on reliability. It turns the argument between "go faster" and "be careful" into a shared number agreed in advance.

What is burn rate? Why is it better than the raw error rate? (Must know)

Burn rate is the error ratio divided by the error budget. At burn rate 1 the budget lasts exactly the SLO window. At 10 it is gone in a tenth of the window, so 3 days out of 30. It is better than a raw error rate because it does not depend on the SLO: 1% errors is urgent for a 99.9% service and different for a 99% one, while burn rate 10 has the same meaning for both. That lets me write one alert rule for all services.

Your service hit its SLO this month with 40% of the budget unused. Is that good? (Trap)

It is fine, but it is not automatically good. An unspent budget can mean the team is too cautious. If it is repeated for months, I would ask whether the SLO is too loose, or whether we should ship faster and take more risk. Reliability above what users need is a cost. The goal is to spend the budget on useful change, not to hoard it.

What would you do when the error budget runs out? (Must know)

I follow the budget policy that was agreed beforehand. Typically that means a freeze on risky feature work, and only reliability and security changes ship until the SLI recovers. I look at what spent the budget (the cost per cause), fix the top one, add tests or guards, and keep the post-mortem. The value of the policy is that the freeze is not a negotiation at that moment. If there is no policy, the first thing I do is write one with the product owner.

How do you set the SLO target? Why not just aim for 100%? (Senior signal)

I start from what users need and what the system has actually achieved over recent months, then pick a target the team can meet and tighten later. 100% is a trap: it is not reachable because networks, clouds and user devices fail, it means any change is unacceptable because the budget is zero, and each extra nine costs about ten times more for less and less visible benefit. I also check the dependencies, because my service cannot honestly beat the product of the services it needs in series.

Why is a latency SLO written as "99% of requests under 300 ms" and not "average latency under 200 ms"? (Senior signal)

An average hides the slow tail, and the tail is what annoying users feel. A p99 target is better, but percentiles cannot be added up across servers or time. A ratio of counts can be added over any period and any fleet, so tools can compute it exactly from a histogram bucket. For that, I need a bucket boundary exactly at my threshold, which I choose when I design the metric.

Your SLO dashboard is green but customers complain. What do you check? (Senior signal)

I treat it as a bug in the SLI. I check whether I measure in the right place (a crash before my app code runs shows as no data, not as errors), what is in the denominator (health checks and bots make things look better), whether latency is measured at all, whether errors that users feel, like 429 or empty results, are counted as good, and whether one important endpoint is hidden among cheap traffic. Then I fix the definition and compare it against support data.

Your service needs three dependencies, each 99.9%, in series. What availability can you promise? (Trap)

About 99.7%, because for independent parts in series I multiply the availabilities: 0.999 cubed. That is more than two hours of downtime a month, not 43 minutes. So I cannot honestly promise 99.9% unless I reduce the coupling: make dependencies optional with a fallback, add redundancy, cache, or improve the weakest link. I also point out that the multiplication assumes independent failures, and shared causes make things worse than the maths says.

How is a rolling window different from a calendar window? (Senior signal)

A rolling window (the last 30 days) always moves, so a bad day keeps counting until it leaves the window. That reflects how users remember and is harder to game. A calendar window resets on the first of the month, which is easier to report but creates bad incentives: no care after you blow the budget early, and risk-taking at the end of a good month because it resets soon. I prefer rolling for decisions and alerts, and calendar for reports if needed.

Time-based or request-based availability? (Senior signal)

Request-based. It counts what users actually tried to do. In my simulation the same 10-minute total outage used 40.5% of the month's budget at peak and 5.8% at the quietest time, while a time-based number says 23% in both cases. Time-based is easy to explain but ignores the difference in impact. The catch for request-based is low-traffic services, where I add synthetic probes or use longer windows so a few requests do not dominate.

Who owns the SLO? Who decides the target? (Senior signal)

The team that runs the service owns the SLI and the work to meet it. But the target is a business trade-off, so the product owner has to agree to it and to the budget policy. If engineering sets it alone, nobody else respects a freeze. If product sets it alone, it is usually too high. It should be reviewed regularly against support tickets and cost.

A service has an SLA of 99.9% and an internal SLO of 99.9%. What is wrong? (Trap)

There is no margin. We will find out about trouble at the same time we owe a refund. I would set the SLO tighter than the SLA, for example 99.95%, so alerts and the budget policy kick in before we breach the contract.

Key takeaways

  • Pick SLIs from the user's side: availability and latency of the main journeys. Write them as good events over valid events, and define "valid" on paper.
  • Latency SLIs are the share of requests under a threshold, not an average, and your histogram needs a bucket at that threshold.
  • An SLO is an SLI, a target and a window. Never 100%. Rolling windows are harder to game.
  • Learn the nines: 99.9% is about 43 minutes a month, 99.99% about 4. Each nine is ten times less room and a lot more cost.
  • Dependencies in series multiply: three at 99.9% make 99.7%. Redundancy in parallel and soft dependencies raise it.
  • The error budget is 1 minus the SLO, and it is meant to be spent on change. Count it in requests, and show the percentage remaining and the cost per cause.
  • Burn rate = error ratio / error budget. It works for any SLO, which is why alerts use it.
  • Write an error budget policy with the product owner while it is calm, so a freeze is a rule and not an argument.
  • If the dashboard is green and users are unhappy, the SLI is wrong, not the users.

What's next

Next: Alerting and Dashboards That People Trust. We use the budget and the burn rate from this lesson to decide who should be woken up, with real alert rules checked by promtool, and a simulation that shows which alerts fire during a blip, a slow leak and a real outage. Practise now: write one availability SLI and one latency SLI for the most important endpoint in a service you know. For each, write down what is valid, what is good and where you would measure it. Then work out its budget in requests per month.

Published by Jainik · Last updated · How these lessons are made

Keep learning

Part of the study guide

Related series